AQW 27868/22-27 – Wastewater Treatment Works at the Loup

Mr Patsy McGlone (Mid Ulster): To ask the Minister for Infrastructure when the Wastewater Treatment Works at the Loup, Mid Ulster, will be fully operational.

Minister for Infrastructure: The management of public wastewater infrastructure is an operational matter for NI Water. However, I have sought the requested information from NI Water and have been advised as follows:

NI Water is currently undertaking base maintenance work at the Loup wastewater treatment works (WwTW) and that work is nearing completion. The Loup WwTW remains fully operational while this work is ongoing.

For any future queries relating to operational matters, you should contact NI Water directly, through the Elected Representatives Hotline on 0345 300 6461 or through waterline@niwater.com

Making direct contact with NI Water will ensure that you receive the information in the shortest possible timeframe and make best use of limited public resources.

ENDS