AQW 26916/22-27 – New social homes construction in Banbridge

Mr Patsy McGlone (Mid Ulster): To ask the Minister for Communities to detail the number of new social homes programmed for starting on-site in Banbridge in the next two years.

Minister for Communities: This issue is an operational matter for the Northern Ireland Housing Executive.
I have sought the requested information from the Chief Executive, who has advised me as follows:

‘There are 47 social homes programmed to start as part of the Social Housing Development Programme (SHDP) 2025/26 – 2026/27. The detail of these units is provided in Table 1 below.

Programmed schemes can be lost or slip to future programme years for a variety of reasons e.g. relating to delays in acquiring sites and/or failure to secure Planning Approval. Additional schemes can also be added to the SHDP ‘in-year’ through Competitive Land, Design & Build procurement route and/or the purchase of Existing Satisfactory / Off-the-Shelf properties.

Table 1: Social housing units programmed to start in Banbridge.

Housing AssociationHE RegionLocal Government DistrictParliamentary ConstituencyScheme NameLocationTypeNeed GroupStrategic GroupUnitsOnsite YearCompletionYear
Arbour HousingSouthArmagh Banbridge & CraigavonUpper Bann40 Fort StreetBanbridgeReimprovementGeneral NeedsUrban12025/262025/26
ClanmilSouthArmagh Banbridge & CraigavonUpper BannThe CoachBanbridgeNew BuildGeneral NeedsUrban442025/262027/28
ClanmilSouthArmagh Banbridge & CraigavonUpper BannThe CoachBanbridgeNew BuildWheelchair StandardUrban22025/262027/28

For any future queries relating to operational matters, you may wish to contact the Northern Ireland Housing Executive directly at Public.Affairsunit@nihe.gov.uk

Making direct contact with the ALB will ensure that you receive the information in the shortest possible timeframe and make the best use of public resources.

ENDS