AQW 41717/22-27 – Repair and Maintenance at Holywell Hospital, Antrim

Mr Patsy McGlone (Mid Ulster): To ask the Minister of Health to detail the total cost of (i) maintenance; (ii) repair; and (iii) any capital and revenue projects, at Holywell Hospital, Antrim, in each of the last ten years.

Minister of Health: The detail is broken down in the table below.

YearMaintenance & RepairCapital ProjectsRevenue ProjectsTotal
2016/17£936,666£106,180£17,847£1,060,693
2017/18£695,354£182,220£29,643£907,217
2018/19£790,121£73,000£30,390£893,511
2019/20£901,472£949,768£85,013£1,936,253
2020/21£895,036£465,262£358,922£1,719,220
2021/22£956,509£995,858£78,420£2,030,787
2022/23£796,331£1,373,691£292,761£2,462,783
2023/24£878,623£1,803,566£57,580£2,739,769
2024/25£948,721£925,949£344,437£2,219,107
2025/26 *£1,054,967£909,810£0£1,964,777

*Note that these costs are up to 15 March 2026. The final quarter figures will not be available until after the financial year has closed for year-to-date 2025/26.